Project Description

Woodbridge Energy Center

Date: 2014

Location: Woodbridge, New Jersey

Client: Kiewit Power

Project scope included HRSG Large Bore pipe fabrication for the Woodbridge Energy Center. The project included weld in valves to previous carbon steel and chrome alloys spools completed during CMI Energy fabrication. It also included fabrication of 71 lifting lugs.

To learn more about Kiewit’s involvement, click here. To learn more about the CPV Woodbridge Energy Center, click here.

Photo courtesy of CPV, Competitive Power Ventures.